2706 West Colorado Boulevard - 102 UNIT 102
Approval Needed – Tub Manifold & Drain Repair / Owner Approved
Photos
Completed
Days open: 146
Warranty / owner-preferred contractor
Assignment
Jorge ortiz
Scheduled: 01/27/2026
Unit Maintenance Profile
View full unit profile
BA unit id: 319
•
PM unit id: 1239197
Unit maintenance sections are not available.
Completion
Completion date
27-Jan, 9:00 am
Completion notes
Move range and remove the panel under the counter on the kitchen side. Remove a 2'x3' section of sheetrock from the shared wall between the bathroom and the kitchen to gain access to the shower faucet manifold. Remove damaged manifold and replace with new single handle manifold. Test water supply line for leaks. Install all the fixtures(spout, handle, and shower head. Remove drain to the tub and replace with new drain.
Drain could not be replaced because a big part of pvc drain pipe was damaged and leaking water it will have to be replaced together with the overflow pipe. We checked the water heater when we were there as instructed and water heater needs to be replaced. Sending estimate for pvc pipe repair underneath building in crawl space and replacing the water heater.
Messages
No messages found for this meld yet (or sync hasn’t pulled them in).
Send a message
Choose recipients, then send.
Recipients
Contacts
Assignment
Jorge ortiz
This updates our dispatch assignment (and can differ from Property Meld until scheduled).
Technician / Vendor Assigned
Jorge ortiz
Scheduled: 01/27/2026
AI Coordinator Assistant Click to expand
Suggestion
—